Park House Office Accommodation London W1
Power load assessment with 7 days data logging following UKPN indication that maximum load was being exceeded. Review of laundry plant operating times to avoid peak morning kitchen power loads 'smoothed' the simultaneous peak loads avoiding the need for a 120K spend on a sub station, together with the associated 25msq footprint
Review of the plant operation and luminaires avoided the need for a £120k spend on a new sub station with a power load assessment with 7 day data logging.